If a subcontractor sends you a payment claim and you disagree with the amount, check when it was served before you start arguing about the figures. The deadline for your response may already be running.
It’s easy to miss a claim when it goes to the accounts inbox. It may look like an invoice waiting for the project manager’s sign-off. Give someone responsibility for checking the deadline while the site team looks into the work.
Is it a claim under the Act?
A payment claim under the Building and Construction Industry Security of Payment Act 2002 must identify the work, goods or services it covers, state the amount claimed and say it is made under the Act. It can look like an ordinary invoice, so read the whole document and keep a copy of the email or other record of service.
The Act applies to many construction contracts, with exceptions including certain domestic building contracts. The changes that started on 15 April 2026 can also affect contracts signed before that date. If you’re dealing with an earlier claim or an adjudication that was already under way, check the transitional arrangements explained by the Building and Plumbing Commission.
When is the payment schedule due?
If you intend to pay less than the full amount, or nothing at all, you generally have 10 business days from service of the claim to serve a payment schedule. A shorter period in the contract can apply. Check both how the claim was served and how you need to serve your response. The date to pay and the date to respond can be different. When calculating the deadline, the Act’s definition of “business day” excludes Saturdays, Sundays, Victorian public holidays and the period from 22 December to 10 January inclusive.
An email saying you’re looking into the claim may leave the deadline running. If time is tight or you think the date has passed, get advice while your team pulls the documents together.
Explain each amount you dispute
Your payment schedule needs to identify the claim and say how much you propose to pay. If that figure is lower than the amount claimed, set out the reasons for the difference. If you propose to pay nothing, say so and explain why.
Say the claim includes $18,000 for weekend work. Check the instruction, the rate and the site records. If you accept some of the hours but dispute the rest, show how you reached your figure. Under the amended Act, you generally can’t add fresh reasons for withholding payment in an adjudication response, so deal with each disputed item in the schedule.
What to keep on file
- The claim and the record showing when and how it was served.
- The signed contract, any amendments, and the payment and service clauses.
- A line-by-line comparison of what was claimed and what you accept.
- Variation instructions, site diaries, photos and defect reports that explain any difference.
- Your payment schedule and proof of when and how you served it.
If a valid claim goes unanswered and you miss the payment due date, the claimant may be able to enforce the full amount claimed. Get advice about any options still open to you, even if you have good reasons to dispute the work.